task completed! Notice to Proceed January 8, 2001
 task completed! Kick-off Meeting January 17, 2001
 task completed! Presentation to Somerset Chamber of Commerce and the Casselman Valley Planning Group January 18, 2001
 task completed! Public Meeting to Introduce Project April 30, 2001
 task completed! Preliminary Alternatives Analysis Fall 2001
 task completed! Public Meeting to Present Preliminary Alternatives December 13, 2001
 task completed! Detailed Alternatives Development and Review Spring/Fall 2002
 task completed! Somerset County Fair August 17-24, 2002
 task completed! Public Meeting to Present Detailed
Alternatives Analysis
October 24, 2002
 task completed! Agency Coordination Meeting March 2003
 task completed! Somerset County Fair August 16-23, 2003
 task completed! Draft Environmental Impact Statement (EIS) Preparation and Circulation Fall 2004
 task completed! Public Hearing/Plans Display November 15, 2004
 task completed! End of DEIS/Section 4(f) Evaluation Comment Period

November 30, 2004
 task completed!  Final EIS Preparation and Distribution Summer 2005
  ROD/Approval of Final Alignment

Fall 2005
  Pre-Final Design

Winter 2005/2006
  Final Design/Right-of-Way Acquisition 2006-2007
  Construction to Begin 2008-2009

 