Project Schedule

U.S. 219 Improvements, Meyersdale to I-68 in Maryland

check mark image Public Meeting to Introduce the Project April 30, 2001
check mark image Preliminary Alternatives Analysis Fall 2001
check mark image Public Meeting to Present Preliminary Alternatives Fall 2001
  Detailed Alternatives Analysis Spring/Summer 2002
  Public Meeting to Present Detailed Alternatives Analysis Late Summer/
Fall 2002
  Draft Environmental Impact Statement Winter 2002/2003
  Public Meeting on Draft Environmental Impact Satement Winter 2002/2003
  Final Environmental Impact Statement Spring 2003
  Pre-Final Design Fall 2003

Preliminary design work and environmental investigations will begin early this spring on the section of U.S. 219 between the southern end of the Meyersdale Bypass and Interstate 68 in Garrett County, Maryland. McCormick, Taylor and Associates (MTA) has been selected by PENNDOT to complete the preliminary design phase of this 8-mile section of U.S. 219. Information on the project will be available on the U.S. 219 website (www.us219.com) and in the project newsletter. PENNDOT and MTA look forward to working with the Somerset County communities to improve U.S. 219.

Contacts

Dave Sherman, P.E.
Project Manager

PENNDOT 9-0
1620 N. Juniata Street
Hollidaysburg, PA 16648

Elizabeth Estes
Public Involvement Coordinator

Greenhorne & O'Mara, Inc.
5000 Ritter Road, Suite 102
Mechanicsburg, PA 17055
Phone: (717) 691-3355
Fax: (717) 691-3366

PENNDOT logo

Pennsylvania Department of Transportation
1620 N. Juniata Street
Hollidaysburg, PA 16648



Federal Highway Administration logo

Copyright © 2002 by The Pennsylvania Department of Transportation

Valid XHTML 1.0!  Valid CSS!